dátum |
plánovaný
|
odhad NDS
|
2015, osobná + nákladná
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v mesiacoch
za posledný rok |
||||||||||
12 úsekov |
121,2 km |
2 - 6 |
2 670 mil. € |
3 407 - 54 519 | 2,4 |
2,7 |
2/2026 - 7/2029 | ||||||||||
1 | 33. - 37. | 2/2023 | ![]() | R2 | 9,6 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 112 mil. € | 8 634 - 11 116 | 3 | 2 | nezačaté | 10/2021 | 2/2026 (+9) | |||
2 | 33. - 37. | 2/2023 | ![]() | D1 | 19,9 km | 6 | D 33,5/120 | 277 mil. € | 42 774 - 54 519 | . . . | 2 | 2 | nezačaté | 4/2022 | |||
3 | 33. - 37. | 2/2023 | ![]() | D4 | 12,4 km | 4 | D 26,5/120 (tunel 2 x T 8,0/100) | 771 mil. € | 2 | 4 | nezačaté | 7/2029 (-8) | |||||
4 | 33. - 37. | 2/2023 | ![]() | R3 | 4,9 km | 2 | R 24,5/80, plánované v 1/2-profile | 77 mil. € | 2 | 2 | nezačaté | 11/2021 | 2/2026 (+18) | ||||
5 | 33. - 37. | 2/2023 | ![]() | R3 | 8,3 km | 2 | R 24,5/80, plánované v 1/2-profile | 201 mil. € | 5 550 - 9 787 | 2 | 3 | nezačaté | 11/2021 | 2/2026 (+18) | |||
6 | 38. | 3/2023 | ![]() | R2 | 16,0 km | 4 | R 24,5/120(100) | 274 mil. € | 9 654 - 12 079 | 2 | 2 | nezačaté | 1/2022 | 3/2026 (+8) | |||
7 | 39. | 5/2023 | ![]() | R2 | 11,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 235 mil. € | 7 793 | 3 | 3 | nezačaté | 1/2022 | 5/2026 (0) | |||
8 | 40. | 8/2023 | ![]() | R4 | 4,0 km | 4 | R 24,5/100 | 102 mil. € | 14 625 | 2 | 2 | nezačaté | 4/2022 | 8/2026 (+10) | |||
9 | 41. | 10/2023 | ![]() | R2 | 17,5 km | 4 | R 24,5/100 | 287 mil. € | 12 819 - 29 988 | 2 | 2 | nezačaté | 8/2022 | 10/2026 (+27) | |||
10 | 42. | 11/2023 | ![]() | D4 | 3,6 km | 4 | D 26,5/100 | 133 mil. € | 5 | 5 | nezačaté | 11/2026 (-21) | |||||
11 | 43. - 44. | 12/2023 | ![]() | R4 | 6,5 km | 2 | R 24,5/100, plánované v 1/2-profile | 105 mil. € | 6 651 - 9 113 | 2 | 3 | nezačaté | 8/2022 | 12/2026 (+3) | |||
12 | 43. - 44. | 12/2023 | ![]() | R4 | 7,0 km | 2 | R 24,5/100, plánované v 1/2-profile | 97 mil. € | 3 407 - 3 769 | 2 | 2 | nezačaté | 8/2022 | 12/2026 (+3) | |||
12 úsekov |
121,2 km |
2 - 6 |
2 670 mil. € |
3 407 - 54 519 | 2,4 |
2,7 |
2/2026 - 7/2029 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku