dátum |
odhad NDS
|
2015, osobná + nákladná
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v mesiacoch
za posledný rok |
||||||||||
1 | 13. | 4/2021 | ![]() | R4 | 8,2 km | R 24,5/100, plánované v 1/2-profile | 96 mil. € | 4 001 | 3 | 3 | 12/2019 | 4/2023 (+6) | ||||
2 | 14. | 5/2021 | ![]() | R7 | 14,3 km | R 11,5/120 | 98 mil. € | 4 | 4 | 11/2025 (+8) | ||||||
3 | 15. - 16. | 6/2021 | ![]() | R2 | 6,2 km | R 22,5/100, plánované v 1/2-profile | 74 mil. € | 5 304 | 2 | 2 | 12/2019 | 6/2023 (+24) | ||||
4 | 15. - 16. | 6/2021 | ![]() | R1 | 8,1 km | R 22,5/100 | 164 mil. € | 12 387 - 17 316 | 2 | 3 | 4/2020 | 6/2023 (+11) | ||||
5 | 17. | 7/2021 | ![]() | R7 | 11,0 km | R 24,5/120 | 97 mil. € | 6 428 - 9 084 | 4 | 4 | 1/2026 (+10) | |||||
6 | 18. - 21. | 8/2021 | ![]() | R7 | 23,5 km | R 11,5/120 | 161 mil. € | 4 | 4 | 2/2026 (+11) | ||||||
7 | 18. - 21. | 8/2021 | ![]() | R2 | 8,3 km | R 22,5/100, plánované v 1/2-profile | 92 mil. € | 5 277 - 6 250 | 2 | 2 | 1/2020 | 8/2023 (+26) | ||||
8 | 18. - 21. | 8/2021 | ![]() | D1 | 10,6 km | D 41/120 | 216 mil. € | 62 652 | . . . | 1 | 1 | 10/2019 | ||||
9 | 18. - 21. | 8/2021 | ![]() | R1 | 2,7 km | R 24,5/80 | 62 mil. € | 16 268 | 3 | 3 | 11/2020 | 8/2023 (+8) | ||||
10 | 22. | 12/2021 | ![]() | D3 | 4,0 km | D 24,5/80 | 103 mil. € | 15 053 | 2 | 2 | 6/2020 | 12/2024 (+6) | ||||
10 úsekov |
96,9 km |
1 163 mil. € |
4 001 - 62 652 | 2,7 |
2,8 |
4/2023 - 2/2026 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku