dátum |
plánovaný
|
odhad NDS
|
2015, osobná + nákladná
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v mesiacoch
za posledný rok |
||||||||
1 | 74. | 5/2029 | ![]() | D2 | 8,5 km | 6 | 90 mil. € | 32 968 | . . . | 5 | 5 | 10/2027 | 5/2032 (+26) | ||
2 | 72. - 73. | 2/2029 | ![]() | D2 | 6,9 km | 6 | 106 mil. € | 5 | 5 | 8/2027 | 2/2032 (+27) | ||||
3 | 62. - 71. | 11/2027 | ![]() | R3 | 10,4 km | 2 | 243 mil. € | 7 211 | 4 | 4 | 8/2026 | 11/2030 (+17) | |||
4 | 75. - 76. | 6/2030 | ![]() | R3 | 14,0 km | 2 | 305 mil. € | 4 | 3 | 8/2028 | 6/2033 (+21) | ||||
5 | 75. - 76. | 6/2030 | ![]() | R2 | 49,0 km | 2 | 662 mil. € | 5 762 - 14 648 | 4 | 4 | 8/2028 | 6/2033 (+21) | |||
6 | 62. - 71. | 11/2027 | ![]() | R3 | 6,7 km | 2 | 251 mil. € | 8 973 - 10 745 | 3 | 5 | 8/2026 | 11/2030 (+45) | |||
7 | 72. - 73. | 2/2029 | ![]() | R8 | 54,9 km | 4 | 1 020 mil. € | 4 151 - 11 477 | 3 | 5 | 9/2027 | 2/2034 | |||
8 | 62. - 71. | 11/2027 | ![]() | R3 | 1,9 km | 2 | 31 mil. € | 5 586 | 2 | 2 | 8/2026 | 11/2030 (+45) | |||
8 úsekov |
152,3 km |
2 - 6 |
2 710 mil. € |
4 151 - 32 968 | 3,8 |
4,1 |
11/2030 - 2/2034 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku