dátum |
odhad NDS
|
2015, osobná + nákladná
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v mesiacoch
za posledný rok |
||||||||||
20 úsekov |
220,9 km |
3 802 mil. € |
1 698 - 18 874 | 3,7 |
3,3 |
1/2028 - 11/2030 | ||||||||||
1 | 33. - 37. | 2/2023 | ![]() | D4 | 12,4 km | D 26,5/120 (tunel 2 x T 8,0/100) | 771 mil. € | 2 | 4 | 7/2029 (-8) | ||||||
2 | 51. | 1/2025 | ![]() | R4 | 7,9 km | R 24,5/100, plánované v 1/2-profile | 127 mil. € | 2 552 - 2 737 | 4 | 3 | 8/2023 | 1/2028 (+12) | ||||
3 | 52. | 4/2025 | ![]() | R2 | 9,8 km | R 24,5/120, plánované v 1/2-profile | 93 mil. € | 6 452 - 10 032 | 5 | 5 | 11/2023 | 4/2028 (+14) | ||||
4 | 53. | 5/2025 | ![]() | R2 | 14,0 km | R 24,5/120, plánované v 1/2-profile | 117 mil. € | 5 809 - 8 826 | 5 | 4 | 1/2024 | 6/2028 (+15) | ||||
5 | 54. | 6/2025 | ![]() | R2 | 18,0 km | R 24,5/120, plánované v 1/2-profile | 175 mil. € | 5 189 - 6 389 | 5 | 5 | 1/2024 | 6/2028 (+14) | ||||
6 | 55. - 57. | 7/2025 | ![]() | R4 | 8,0 km | R 24,5/100, plánované v 1/2-profile | 132 mil. € | 5 814 - 7 518 | 4 | 3 | 2/2024 | 7/2028 (+15) | ||||
7 | 55. - 57. | 7/2025 | ![]() | R4 | 7,5 km | R 24,5/100, plánované v 1/2-profile | 123 mil. € | 3 769 - 3 897 | 3 | 3 | 2/2024 | 7/2028 (+15) | ||||
8 | 55. - 57. | 7/2025 | ![]() | R4 | 6,0 km | R 24,5/100, plánované v 1/2-profile | 100 mil. € | 3 782 - 6 302 | 4 | 3 | 2/2024 | 7/2028 (+15) | ||||
9 | 60. - 61. | 1/2026 | ![]() | R3 | 7,9 km | R 24,5/120(100), plánované v 1/2-profile | 71 mil. € | 5 441 - 8 427 | 4 | 3 | 9/2024 | 1/2029 (+5) | ||||
10 | 60. - 61. | 1/2026 | ![]() | R3 | 14,0 km | R 24,5/120 (100) | 191 mil. € | 14 233 - 18 874 | 3 | 3 | 10/2024 | 1/2029 (+19) | ||||
11 | 62. - 71. | 11/2026 | ![]() | D1 | 12,6 km | D 26,5/120
(100) | 418 mil. € | 9 503 - 9 802 | 3 | 3 | 6/2025 | 11/2029 (+14) | ||||
12 | 62. - 71. | 11/2026 | ![]() | D1 | 18,2 km | D 26,5/120
(100) | 191 mil. € | 6 207 - 8 525 | 3 | 2 | 6/2025 | 11/2029 (+14) | ||||
13 | 62. - 71. | 11/2026 | ![]() | R6 | 11,3 km | R 11,5/100 (80) | 142 mil. € | 7 234 | 4 | 3 | 9/2025 | 11/2029 (+7) | ||||
14 | 62. - 71. | 11/2026 | ![]() | D1 | 15,8 km | D 26,5/120
(100) | 138 mil. € | 4 033 - 8 369 | 4 | 3 | 6/2025 | 11/2029 (+11) | ||||
15 | 62. - 71. | 11/2026 | ![]() | D1 | 12,1 km | D 26,5/120
(100) | 162 mil. € | 10 444 - 14 783 | 3 | 2 | 6/2025 | 11/2029 (+11) | ||||
16 | 62. - 71. | 11/2026 | ![]() | D1 | 15,5 km | D 26,5/120
(100) | 135 mil. € | 1 698 - 6 812 | 4 | 3 | 6/2025 | 11/2029 (+11) | ||||
17 | 62. - 71. | 11/2026 | ![]() | R6 | 11,0 km | R 11,5/100 (80) | 190 mil. € | 2 561 - 5 054 | 4 | 3 | 9/2025 | 11/2029 (+7) | ||||
18 | 62. - 71. | 11/2027 | ![]() | R3 | 10,4 km | R 24,5/80, plánované v 1/2-profile | 243 mil. € | 7 211 | 4 | 4 | 8/2026 | 11/2030 (+17) | ||||
19 | 62. - 71. | 11/2027 | ![]() | R3 | 6,7 km | R 24,5/80, plánované v 1/2-profile | 251 mil. € | 8 973 - 10 745 | 3 | 5 | 8/2026 | 11/2030 (+45) | ||||
20 | 62. - 71. | 11/2027 | ![]() | R3 | 1,9 km | R 24,5/80, plánované v 1/2-profile | 31 mil. € | 5 586 | 2 | 2 | 8/2026 | 11/2030 (+45) | ||||
20 úsekov |
220,9 km |
3 802 mil. € |
1 698 - 18 874 | 3,7 |
3,3 |
1/2028 - 11/2030 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku