dátum |
jednostranné / obojstranné
|
odhad NDS
|
2015, osobná + nákladná
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v mesiacoch
za posledný rok |
|||||||||
1 | 72. - 73. | 2/2029 | ![]() | D2 | 6,9 km | D 33,5/120 | 106 mil. € | 5 | 5 | 8/2027 | 2/2032 (+27) | |||||
2 | 72. - 73. | 2/2029 | ![]() | R8 | 54,9 km | R 24,5/100 | 1 020 mil. € | 4 151 - 11 477 | 3 | 5 | 9/2027 | 2/2034 | ||||
3 | 74. | 5/2029 | ![]() | D2 | 8,5 km | D 33,5/120 | Stupava | 90 mil. € | 32 968 | . . . | 5 | 5 | 10/2027 | 5/2032 (+26) | ||
4 | 75. - 76. | 6/2030 | ![]() | R3 | 14,0 km | R 24,5/120(100), plánované v 1/2-profile | Sklené | 305 mil. € | 4 | 3 | 8/2028 | 6/2033 (+21) | ||||
5 | 75. - 76. | 6/2030 | ![]() | R2 | 49,0 km | R 24,5/120(100), plánované v 1/2-profile | 662 mil. € | 5 762 - 14 648 | 4 | 4 | 8/2028 | 6/2033 (+21) | ||||
5 úsekov |
133,3 km |
2 183 mil. € |
4 151 - 32 968 | 4,2 |
4,4 |
2/2032 - 2/2034 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku